image
PT.MALMASS MITRA TEKNIK PROJECT
REVITALISASI GEDUNG TEKNOGAS, GEOFISIKA & APLIKASI

Location: Cipulir – South Jakarta

PROJECT DATA:
Owner: PPPTMGB - LEMIGAS
(Pusat Penelitian & Pengembangan Teknologi Minyak & Gas)
Architect: PT. Pusparaya Karsa Per&a

Building Area:
- Laboratorium Teknogas = 2.124 m²
- Laboratorium Geofisika = 928 m²
- Laboratorium Aplikasi = 4.074 m²

Total Floor:
- Laboratorium Teknogas, 2 Storey
- Laboratorium Geofisika, 2 Storey and
- Laboratorium Aplikasi, 2 Storey

Function Building: Laboratorium
Year:
2009

MEP SYSTEM:
ACMV System: AC Split Duct, Ducting, AC Split Wall Mounted and Mechanical Ventilation System

Plumbing System:
- Clean water, Waste water, Ventilation and Rain water, etc
- GWT Lab. Teknogas = 75 m³ (Source; PDAM & Deepwell)
- GWT Lab. Geofisika = 35 m³
- GWT Lab. Aplikasi = 150 m³, Total 260 + 250 = 510 m³
- STP cap.250 m³/day, Aeration system

Fire Fighting System:
- Hydrant, Sprinkler and Foam Gas System
- Electric Hydrant Pump (EHP), 750 us gpm, head 150 m’
- Electrical Characteristics; 380 Volt, 3 Ph, 50 Hz

Electrical System:
- Electrical Load; PLN 865 kVA (Source; PLN & Genset),
- Transformers Oil type, 1 x 630 kVA, TM 20 kV – 380 Volt l Diesel Generator Set, 1 x 630 kVA, Prime power type for 3 Buildings
Lightning System: Conventional System
Telecommunication System: PABX, 100 Direct Lines – 1.000 Extention, to PT. Telkom
Fire Alarm System: Semi Addressable System, 4 Loop – 900 points
Sound System: Public Address and Evacuation System
Security System: MATV System and CCTV System

Ancillary:
- Local Area Network (LAN).
- Building Automation System (BAS)
- GAS Installations
- IPAL

Gededung Geoeofisika and Aplikasasi:
ACMV System: AC Split Duct, Ducting, AC Split Wall Mounted and Mechanical Ventilation System
Plumbing System: Clean Water, Waste Water, Ventilation and Rain Water, etc

Fire Fighting System:
- Hydrant, Sprinkler and Foam Gas System
- Electric Hydrant Pump (EHP), 750 us gpm, head 150 m’
- Electrical Characteristics; Volt, 3 Ph, 50 Hz

Lift/Elevator System:
- 3 Unit Lift Passengers, 17 persons/1500kg, 60 mpm
- 3 Unit Lift Service, 1500kg, 60 mpm

Electrical System: Electrical Load; PLN 865 kVA (Source; PLN & Genset),
Lightning System: Conventional System
Telecommunication System: PABX, 100 Direct Lines – 1.000 Extention, to PT. Telkom
Fire Alarm System: Semi Addressable System
Sound System: Public Address and Evacuation System
Security System: MATV System and CCTV System

Ancillary:
- Local Area Network (LAN)
- Building Automation System (BAS)
- GAS Installations
- IPAL